Slab steel before the pour on Kalkallo lots

Top bars, cover, chairs and laps: what we check on a Kalkallo slab the day before concrete.

Kalkallo 3064 · 18 August 2026

In short: Beam steel decides how a slab copes with reactive clay. The day before the pour is the only time you can check it matches the engineering.

Top bars and beam steel

Extra top bars shown on the engineering are the item we most often find missing on Kalkallo slabs.

Cover and chairs

Steel touching the formwork or sagging between chairs ends up with too little concrete around it, inviting corrosion.

Laps

Bars and mesh need to overlap by set lengths for each size. Short laps weaken the joint.

Everything else on the deck

Loose pods, uncapped pipes, set-downs not formed and debris left in the beams all get listed.

Written by our local inspection team from work carried out in Kalkallo. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.

Guides

More new construction stage inspections guides for Kalkallo

All guides →

Book a building inspection in Kalkallo

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Questions Kalkallo owners ask about this

Can the steel be checked after the pour?

No.

How long is the visit?

About an hour.

What if the concreter is booked for the morning?

We can usually attend the afternoon before.

Which standard applies?

AS 2870, with the engineering for your lot.